Not six tonnes
A 60 m² patio on 150 mm of compacted MOT Type 1 needs about 9.6 tonnes. Guess low and you've eaten the margin before the first slab goes down.
Twenty years on the tools · then the software
PriceM8 works out the materials, the labour, the waste and the VAT for landscaping and garden room jobs — then puts it on a quote the customer takes seriously. No spreadsheet. No "I'll ring you with a number."
Built in the UK · priced in £ · VAT where it belongs

These are the three that catch people out most. None of them are complicated. All of them are easy to get wrong standing in someone's back garden with a tape measure in one hand.
A 60 m² patio on 150 mm of compacted MOT Type 1 needs about 9.6 tonnes. Guess low and you've eaten the margin before the first slab goes down.
Dig out a cubic metre and it doesn't compact back to a cubic metre — excavated soil bulks by around 20%. Guess the raw volume and you'll under-order the skip.
Your day rate isn't your cost. Van, fuel, insurance, the hour loading up, the trip to the merchant you didn't plan on. It all lands somewhere.
PriceM8 does all three before you've got back in the van — and shows you the working, so you can argue with it.
Skilled rate, labourer rate, the split, and your own margins — set once in Settings, not guessed per job.
Not a general-purpose quoting app with a landscaping label stuck on it. Two build types, taken off the way you'd take them off yourself — if you had a quiet hour and nobody ringing you.
Drop in the dimensions and the build-up. It takes off the sub-base by tonne at your compacted depth, the bedding, the slabs plus a waste allowance, the jointing, the edgings, the muck away — and the hours.
Every line, not a sample — missing one is how a patio stops being profitable.
A £28,000 build has three hundred things in it and any one of them can be the one you forgot. It generates the timber list at 400mm stud centres, the insulation and membranes, the cladding with a real waste allowance, the roof and the first fix.
All of it, every time — that's the point of not doing this from memory.
Before it, you're standing in a garden with a tape measure and a customer who wants a number. After it, you're chasing a deposit. PriceM8 covers both ends, so it isn't one more app to juggle.
Most quotes lose on the page, not on the number. A single line saying "Patio — £9,700" invites a haggle. A broken-down one invites a deposit.
Job
Rear garden patio — 60 m² porcelain, Cheshire
| Item | Amount |
|---|---|
| Excavate and cart away60 m² × 250 mm · 4 grab loads | £1,140.00 |
| MOT Type 1 sub-base9.6 t · compacted to 150 mm | £612.00 |
| Sharp sand and cement bed40 mm · 2.4 t sand, 12 bags | £288.00 |
| Porcelain paving, 900×60060 m² + 8% cuts and waste | £2,916.00 |
| Jointing compound6 mm joints · 5 tubs | £245.00 |
| Labour2 operatives × 6 days | £2,880.00 |
"If it doesn't survive a wet Tuesday in February, it doesn't go in."
I laid my first patio in 2005. For most of the twenty years after that I priced work the way nearly everyone does — a pad in the van, a spreadsheet that got copied and broken, and a gut feeling that had been right often enough to trust and wrong often enough to hurt.
The jobs that lost money were never the dramatic ones. They were the ones where the sub-base went in deeper than I'd allowed, or the cuts round a curve ate half a pallet, or I'd quoted five days and it took seven. Small, boring, repeated.
So I started writing the calculations down properly. Then I started checking them against jobs I'd already finished and knew the real cost of. Then it stopped being a spreadsheet and became this.
Every figure in PriceM8 came off a real job, not a supplier's brochure and not a language model's best guess. When the numbers are wrong, it's because a merchant changed a price — not because nobody who wrote it had ever held a whacker plate.
Take a job you've already done and put it through. If the number doesn't land within a few percent of what it actually cost you, walk away — that's a fair test and it's the one I'd run.